Chapter 3 – Cost Allocation Project/Department Maintenance
Chapter 3.1 – Cost Allocation Project/Department Maintenance
Maintain Cost Allocation Posting by Project/Department, by asset code as part of general maintenance activities.
This will avoid the need to do it one by one for each asset.
- Go to Asset Register > Cost Allocation Posting Project/Department Maintenance.
2. Click to add a department or project. The total percentage must equal to 100%.
3. The Cost Allocation Posting Project/Department has already been preset as default in Settings.
4. You can select either department or project as posting method.